Huntingdon Borough Paving Project

Grannas Bros. Stone & Asphalt Co. Inc. will be doing the borough’s paving of borough streets.

This is the proposed schedule:

Thursday 7/10/25 – Milling 8th Street – Penn to Washington Street, Milling 12th Street – Moore to Mifflin Street, Warm Springs Avenue Base Repair – Cold Springs Intersection area, N Taylor Avenue 25MM Base

Friday 7/11/25 – Pave 8th Street – Penn to Washington Street, Pave 12th Street – Moore to Mifflin Street, Pave Top on N Taylor Avenue, Warm Springs Top Coat – Cold Springs Road a distance of 250′, Chapel Hill Scratch & Leveling Course

Monday 7/14, 2025 – Chapel Hill Wearing Course, 2RC Stone Shoulder Backup on Warm Springs and N Taylor Avenue